06 Installation

06.1 Scope

This section defines the installation requirements for all MPE i-Series tray sealing machines, including the i5.

These instructions apply to machines supplied by MPE UK Ltd unless otherwise stated in machine-specific documentation.

Installation must only be carried out by:

  • Qualified engineers

  • Authorised installation technicians

  • MPE service personnel or approved partners

Improper installation may result in:

  • Unsafe operation

  • Machine damage

  • Seal quality issues

  • Voiding of warranty

Always refer to the machine data plate and model specification sheet before connecting utilities.


06.2 Delivery and unpacking

Upon delivery, the machine should be inspected before installation.

Inspection Checks

Check the following:

  • No visible transit damage

  • Machine frame is intact

  • Guards are fitted

  • Electrical cabinet is secure

  • Tooling and accessories are present

  • Conveyors and mechanical assemblies are secured

If damage is identified, report immediately to:

  • The site engineering manager

  • MPE UK Ltd support

triangle-exclamation

06.3 Utilities

Utilities must be verified against the machine data plate and specification sheet before connection.

Typical utilities for i-Series machines include:

Electrical Supply

Typical requirements:

  • 3-phase electrical supply

  • Voltage and current rating dependent on model

  • Neutral and earth connection required

Example typical supply:

The electrical supply must be:

  • Correctly protected

  • Installed by a qualified electrician

  • Connected through an accessible isolator


Network / Remote Support

Where fitted, the machine may support remote diagnostics.

Connection options:

  • Ethernet (CAT6)

  • Site Wi-Fi network

Remote access allows MPE engineers to assist with:

  • Fault diagnosis

  • Software updates

  • Performance monitoring


Gas Supply (MAP machines)

Machines equipped with Modified Atmosphere Packaging (MAP) require a gas supply.

Gas type and pressure depend on the packaging process and site configuration.

Typical gases include:

  • Nitrogen (N₂)

  • Carbon Dioxide (CO₂)

  • Gas mixtures

Gas supply must include:

  • Pressure regulation

  • Isolation valve

  • Correct hose connections


Vacuum Supply

Some machines require a vacuum supply for packaging operations.

Where vacuum is installed, ensure:

  • Adequate vacuum level

  • Correct hose connections

  • Isolation capability


Important Utility Warning

triangle-exclamation

06.4 Machine positioning

The machine must be positioned in a location that allows safe operation and maintenance.

Access Requirements

Ensure access to:

  • All guard doors

  • Tooling change areas

  • Film loading system

  • Electrical cabinet

  • Main isolator

Operators must have sufficient space to safely interact with the machine.

Maintenance engineers must have access to service panels and mechanical assemblies.


06.5 Floor requirements

The machine must be installed on a stable and level floor.

Suitable floor types include:

  • Industrial concrete floors

  • Reinforced factory floors

The floor must support the machine weight and operational loads.


06.6 Levelling the machine

Correct machine levelling is essential for proper tray transfer and sealing performance.

Levelling Procedure

  1. Position the machine in its final location.

  2. Adjust the machine levelling feet.

  3. Use a spirit level to confirm the frame is level.

  4. Confirm conveyors are aligned with upstream and downstream equipment.

Improper levelling may cause:

  • Tray misalignment

  • Transfer errors

  • Uneven sealing


06.7 Anchoring (where required)

Some installations require the machine to be anchored to the floor.

Anchoring may be required where:

  • High-speed operation is used

  • Machine stability is critical

  • Site safety requirements demand anchoring

If anchoring is specified:

  1. Mark anchor locations.

  2. Drill floor anchor holes.

  3. Install appropriate anchors.

  4. Secure the machine frame.

Always confirm anchoring requirements with MPE technical documentation.


06.8 Pre-power inspection

Before energising the machine, perform the following checks.

Mechanical Checks

  • No visible transport damage

  • Tooling correctly installed

  • Conveyors correctly mounted

  • Film system components secure


Safety Checks

  • All guards installed

  • Guard interlock switches functional

  • Emergency stop buttons intact

  • No loose components inside the machine

Emergency stops should be checked for mechanical movement only at this stage.

triangle-exclamation

06.9 First energisation

Once installation checks are complete, the machine can be energised.

Power-Up Procedure

  1. Turn the main electrical isolator to ON.

  2. Observe electrical cabinet indicators.

  3. Confirm HMI powers up.

  4. Allow the control system to complete its startup sequence.

The HMI should display the machine interface without critical alarms.

If faults occur during startup, isolate the machine and investigate before continuing.


06.10 Commissioning procedure

Commissioning verifies the machine operates correctly.

Typical commissioning steps include:

Step 1 – Safety Reset

Perform the standard safety reset procedure.

Ensure:

  • Guards closed

  • Emergency stops reset


Step 2 – Axis Homing

The control system will home all servo axes.

This allows the machine to establish reference positions.

Observe machine motion during homing.

triangle-exclamation

Step 3 – Tool Temperature Warm-Up

Activate the sealing tool heating system.

Allow the tool to reach its operating temperature before testing sealing operations.


Step 4 – Dry Cycle Test

Run the machine without trays or film.

This verifies:

  • Mechanical motion

  • Servo movement

  • Transfer system operation


Step 5 – Film Test

Load film and run the machine without trays.

Verify:

  • Film feeding correctly

  • Film tension control working

  • Film tracking correctly


Step 6 – First Product Trial

Load trays and product.

Run the first production cycle and verify:

  • Tray transfer

  • Seal quality

  • Film cutting

  • Pack discharge

Adjust machine parameters if required.


06.11 Seal quality verification

During commissioning, seal quality must be verified.

Checks include:

  • Seal integrity

  • Seal strength

  • Film cut accuracy

  • Pack appearance

Quality checks may include:

  • Visual inspection

  • Peel testing

  • Gas retention tests (MAP machines)


06.12 Integration with production line

The machine may be integrated with upstream or downstream equipment.

Examples include:

  • Tray denesters

  • Filling systems

  • Conveyors

  • Checkweighers

  • Labelling systems

Confirm correct synchronisation with line equipment.


06.13 Operator training

Before production begins, operators must be trained in:

  • Basic machine operation

  • Safety procedures

  • Film loading

  • Recipe selection

  • Basic troubleshooting

Training should be recorded in accordance with site procedures.


06.14 Installation documentation

The following records should be completed during installation.

Minimum documentation should include:

  • Machine model

  • Machine serial number

  • Software version

  • HMI version

  • Installed options

Examples of options include:

  • Gas flush system

  • Registered film

  • Printer integration

  • Remote diagnostics


06.15 Commissioning sign-off

Installation should be signed off by:

  • Installation engineer

  • Site engineering manager

  • Production manager (where required)

Commissioning records should be retained for future reference.

Last updated